FREE BOOKS

Author's List




PREV.   NEXT  
|<   112   113   114   115   116   117   118   119   120   121   122   123   124   125   126   127   128   129   130   131   132   133   134   135   136  
137   138   139   140   141   142   143   144   145   146   147   148   149   150   151   152   153   154   155   156   157   158   159   160   161   >>   >|  
r of the land must qualify himself to superintend his own operations, (with the aid of a country surveyor, or a railroad engineer in the necessary instrumental work.) As draining becomes more general, the demand for professional assistance will, without doubt, cause local engineers to turn their attention to the subject, and their services may be more cheaply obtained. At present, it would probably not be prudent to estimate the cost of engineering and superintendence, including the time and skill of the proprietor, at less than $5 per acre, even where from 20 to 50 acres are to be drained at once. 2. _Digging the Ditches._--The labor required for the various operations constitutes the principal item of cost in draining, and the price of labor is now so different in different localities, and so unsettled in all, that it is difficult to determine a rate which would be generally fair. It will be assumed that the average wages of day laborers of the class employed in digging ditches, is $1.50 per day, and the calculation will have to be changed for different districts, in proportion to the deviation of the actual rate of wages from this amount. There is a considerable advantage in having the work done at some season, (as after the summer harvest, or late in the fall,) when wages are comparatively low. The cutting of the ditches should always be let by the rod. When working at day's work, the men will invariably open them wider than is necessary, for the sake of the greater convenience of working, and the extra width causes a corresponding waste of labor. A 4-foot ditch, in most soils, need be only 20 inches wide at the surface, and 4 inches at the bottom. This gives a mean width of 12 inches, and requires the removal of nearly 2-1/2 cubic yards of earth for each rod of ditch; but an increase to a mean width of 16 inches, (which day workmen will usually reach, while piece workmen almost never will,) requires the removal of 3-1/4 cubic yards to the rod. As the increased width is usually below the middle of the drain, the extra earth will all have to be raised from 2 to 4 feet, and the extra 3/4 yards will cost as much as a full yard taken evenly from the whole side, from top to bottom. In clay soils, free from stones or "hard pan," but so stiff as to require considerable picking, ordinary workmen, after a little practice, will be able to dig 3-1/2 rods of ditch per day, to an average depth of 3.80,--leaving from 2 to 3
PREV.   NEXT  
|<   112   113   114   115   116   117   118   119   120   121   122   123   124   125   126   127   128   129   130   131   132   133   134   135   136  
137   138   139   140   141   142   143   144   145   146   147   148   149   150   151   152   153   154   155   156   157   158   159   160   161   >>   >|  



Top keywords:
inches
 

workmen

 

removal

 
bottom
 

considerable

 

average

 

working

 

requires

 

ditches

 

operations


draining

 
country
 

surface

 
surveyor
 
superintend
 

invariably

 

greater

 

convenience

 

qualify

 

engineer


instrumental

 

railroad

 

stones

 

require

 

picking

 
leaving
 

ordinary

 

practice

 

evenly

 

increased


middle

 

raised

 
increase
 

constitutes

 

principal

 

required

 

Ditches

 

cheaply

 

services

 

difficult


determine
 
engineers
 

unsettled

 

subject

 

attention

 
localities
 

Digging

 
obtained
 
proprietor
 

prudent