FREE BOOKS

Author's List




PREV.   NEXT  
|<   91   92   93   94   95   96   97   98   99   100   101   102   103   104   105   106   107   108   109   110   111   112   113   114   115  
116   117   118   119   120   121   122   123   124   125   126   127   128   129   130   131   132   133   134   135   136   137   138   139   140   >>   >|  
ied up three or four courses to a level with the guidance of the line which is raised course by course, the work should be proved with the level and plumb-rule, particularly with the latter at the quoins and reveals, as well as over the face. A smart tap with the end of the handle of the trowel will suffice to make a brick yield what little it may be out of truth, while the work is green, and not injure it. The work of an efficient craftsman, however, will need but little adjustment. For every wall of more than one brick (9 in) thick, two men should be employed at the same time, one on the outside and the [v.04 p.0522] other inside; one man cannot do justice from one side to even a 14-in. wall. When the wall can be approached from one side only, the work is said to be executed "overhand." In work circular on plan, besides the level and plumb-rule, a gauge mould or template, or a ranging trammel--a rod working on a pivot at the centre of the curve, and in length equalling the radius--must be used for every course, as it is evident that the line and pins cannot be applied to this in the manner just described. Bricks should not be merely _laid_, but each should be placed frog upwards, and rubbed and pressed firmly down in such a manner as to secure absolute adhesion, and force the mortar into joints. Every brick should be well wetted before it is laid, especially in hot dry weather, in order to wash off the dust from its surface, and to obtain more complete adhesion, and prevent it from absorbing water from the mortar in which it is bedded. The bricks are wetted either by the bricklayer dipping them in water as he uses them, or by water being thrown or sprinkled on them as they lie piled on the scaffold. In bricklaying with quick-setting cements an ample use of water is of even more importance. All the walls of a building that are to sustain the same floors and the same roof, should be carried up simultaneously; in no circumstances should more be done in one part than can be reached from the same scaffold, until all the walls are brought up to the same height. Where it is necessary for any reason to leave a portion of the wall at a certain level while carrying up the adjoining work the latter should be racked back, i.e. left in steps as shown in fig. 7, and not carried up vertically with merely the toothing necessary for the bond. [Illustration: FIG. 2.--Section of a Hollow Wall.] Buildings in exposed situations a
PREV.   NEXT  
|<   91   92   93   94   95   96   97   98   99   100   101   102   103   104   105   106   107   108   109   110   111   112   113   114   115  
116   117   118   119   120   121   122   123   124   125   126   127   128   129   130   131   132   133   134   135   136   137   138   139   140   >>   >|  



Top keywords:
carried
 

adhesion

 
wetted
 

mortar

 
scaffold
 

manner

 

setting

 
sprinkled
 

dipping

 

bricklaying


thrown
 

obtain

 

weather

 

joints

 

absorbing

 
bedded
 

bricks

 
prevent
 
complete
 

surface


bricklayer

 

adjoining

 

racked

 

vertically

 

toothing

 

Buildings

 

exposed

 

situations

 

Hollow

 

Section


Illustration
 

carrying

 

floors

 
simultaneously
 

sustain

 

building

 

importance

 

circumstances

 
reason
 
portion

height

 

reached

 
brought
 

cements

 

equalling

 

adjustment

 

craftsman

 

efficient

 

injure

 

employed