FREE BOOKS

Author's List




PREV.   NEXT  
|<   4   5   6   7   8   9   10   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28  
29   30   >>  
fair average sample of the coal used during the test. The condition of the furnace should be the same at the end of the test period as at the start. Therefore, at the moment the test is begun, observe the thickness of the fuel bed and the condition of the fire. If the fire was cleaned, say, an hour before the test began, see that it is cleaned an hour before the time when the test is scheduled to end. If the coal was fired, say, eight minutes before the test started, the last coal used during the test should be fired eight minutes before the end of the test. The object of these precautions is to insure the same conditions at start and finish, as nearly as possible; otherwise, the coal weighed will not be the same as the coal consumed. MEASURING THE FEED WATER. The quantity of water fed to the boiler during the test may be found by metering or by weighing. A reliable water meter is recommended for this work. There are a number of good makes, of different types, such as: 1. Venturi meter. 2. Weir or V-notch meters. 3. Diaphragm meters. 4. Displacement meters. 5. Water weighers. The best form of meter to use in any particular case depends on the local conditions in the plant; but _every plant should be provided with a permanently installed meter of some type_. The displacement form of meter should be used only with cold water, however. If there is no meter or water weigher in the plant, the feed water used during the test can be measured by the three-barrel arrangement illustrated in figure 2. Obtain three water-tight barrels, and set two of them close together on a platform directly over the third, leaving about 12 inches above barrel 3 in which to fit the valves _V_ and the nipples in the bottoms of barrels 1 and 2. Near the top of each of the barrels 1 and 2 screw a 1-inch overflow pipe _O_. Run a pipe _P_ from the city main or other source of supply above barrels 1 and 2, and put a valve _A_ on the pipe leading to each barrel. From barrel 3 run a suction pipe to the feed pump that is to pump water to the boiler to be tested. It is best to have a by-pass from the usual water supply direct to the feed pump, or to another pump connected to the boiler, so that in case of any trouble with the testing barrels, the regular operation of the boiler may be resumed without shutting down. The next step is to fill barrels 1 and 2 with water until they overflow at _O_. This water should b
PREV.   NEXT  
|<   4   5   6   7   8   9   10   11   12   13   14   15   16   17   18   19   20   21   22   23   24   25   26   27   28  
29   30   >>  



Top keywords:

barrels

 

boiler

 
barrel
 
meters
 
conditions
 

supply

 

overflow

 

cleaned

 

condition

 

minutes


arrangement

 

figure

 

illustrated

 

measured

 

weigher

 
inches
 

Obtain

 
leaving
 

valves

 
directly

platform

 

source

 
trouble
 

testing

 

regular

 

operation

 

connected

 

direct

 

resumed

 

shutting


bottoms

 
suction
 

tested

 

leading

 

nipples

 

Displacement

 

finish

 

insure

 

object

 

precautions


weighed

 

quantity

 

consumed

 

MEASURING

 

started

 

Therefore

 
moment
 
period
 
furnace
 

average