FREE BOOKS

Author's List




PREV.   NEXT  
|<   123   124   125   126   127   128   129   130   131   132   133   134   135   136   137   138   139   140   141   142   143   144   145   146   147  
148   149   150   151   152   153   154   155   156   157   >>  
ut the development, stoping, and trucking can be largely managed in this way, and these items cover 65 to 75% of the total labor expenditure underground. In development there are two ways of basing contracts,--the first on the footage of holes drilled, and the second on the footage of heading advanced. In contract-stoping there are four methods depending on the feet of hole drilled, on tonnage, on cubic space, and on square area broken. All these systems have their rightful application, conditioned upon the class of labor and character of the deposit. In the "hole" system, the holes are "pointed" by some mine official and are blasted by a special crew. The miner therefore has little interest in the result of the breaking. If he is a skilled white man, the hours which he has wherein to contemplate the face usually enable him to place holes to better advantage than the occasional visiting foreman. With colored labor, the lack of intelligence in placing holes and blasting usually justifies contracts per "foot drilled." Then the holes are pointed and blasted by superintending men. On development work with the foot-hole system, unless two working faces can be provided for each contracting party, they are likely to lose time through having finished their round of holes before the end of the shift. As blasting must be done outside the contractor's shifts, it means that one shift per day must be set aside for the purpose. Therefore not nearly such progress can be made as where working the face with three shifts. For these reasons, the "hole" system is not so advantageous in development as the "foot of advance" basis. In stoping, the "hole" system has not only a wider, but a sounder application. In large ore-bodies where there are waste inclusions, it has one superiority over any system of excavation measurement, namely, that the miner has no interest in breaking waste into the ore. The plan of contracting stopes by the ton has the disadvantage that either the ore produced by each contractor must be weighed separately, or truckers must be trusted to count correctly, and to see that the cars are full. Moreover, trucks must be inspected for waste,--a thing hard to do underground. So great are these detailed difficulties that many mines are sending cars to the surface in cages when they should be equipped for bin-loading and self-dumping skips. The method of contracting by the cubic foot of excavation saves all n
PREV.   NEXT  
|<   123   124   125   126   127   128   129   130   131   132   133   134   135   136   137   138   139   140   141   142   143   144   145   146   147  
148   149   150   151   152   153   154   155   156   157   >>  



Top keywords:

system

 

development

 

stoping

 

drilled

 
contracting
 
blasting
 

application

 

blasted

 

excavation

 

breaking


pointed

 

interest

 

underground

 

contracts

 

footage

 

shifts

 

working

 
contractor
 

sounder

 

bodies


Therefore
 
purpose
 

inclusions

 

progress

 

reasons

 

advance

 

advantageous

 
disadvantage
 

sending

 

surface


difficulties

 
detailed
 

method

 
dumping
 

equipped

 

loading

 
inspected
 
stopes
 

measurement

 

produced


weighed

 

Moreover

 

trucks

 

correctly

 

separately

 

truckers

 
trusted
 

superiority

 
superintending
 

broken