single flush-deck
letter-of-marque, renamed _Yorktown_; and they had a contract to build
the sloop-of-war _Peacock_. It is remarkable that the Browns could
undertake and complete so much work between 1813 and 1815 and still be
able to build the steam battery in a very short time.
With the contracts in order, the Browns began building. The keels of the
battery were laid June 20, 1814. It is apparent that the Browns prepared
the original hull plans, undoubtedly before the building authority was
obtained. The vessel required only about four months to build; she was
launched October 29, 1814, at 9 a.m. This was an excellent performance,
considering the size of the vessel, the amount of timber required and
handled in her massive construction, and the other work being done by
the builders. During the ship's construction, sightseers were a nuisance
and finally guards had to be obtained. During the building of the steam
battery, work had to be practically stopped on the sloop-of-war
_Peacock_ at one period after she had been partially planked.
There were difficulties in obtaining metalwork for the vessel during her
construction, due to the blockade and the demand for such material for
other shipbuilding at New York. On November 21, 1814, the ship was towed
from the Browns' yard on the East River by Fulton's _Car of Neptune_ and
_Fulton_, each lashed to the sides of the battery, and taken to Fulton's
works on the North River. There Fulton supervised in person the
completion of the vessel and construction of her machinery. Undoubtedly
only a little of his time was required in inspection of the Browns' work
on the battery, for the shipbuilders had been closely associated with
Fulton throughout the life of the project and were fully capable as ship
designers. The work on the machinery was another matter, however, for
men capable of working metal were scarce and few workmen could read
plans. Fulton had some of the work done outside of his own plant,
particularly the brass and copper work (mostly by John Youle's foundry).
As a result, Fulton was required to move from plant to plant, keeping
each job under almost constant observation and personally supervising
the workmen. The equipment then available for building a large engine
was inadequate in many ways. The large steam cylinder presented a
problem: it had to be recast several times and some of the other parts
gave trouble, either in casting or in machining and fitting.
[Illu
|