FREE BOOKS

Author's List




PREV.   NEXT  
|<   212   213   214   215   216   217   218   219   220   221   222   223   224   225   226   227   228   229   230   231   232   233   234   235   236  
237   238   239   240   241   242   243   244   245   246   247   248   249   250   251   252   253   254   255   256   257   258   259   260   261   >>   >|  
unsel together. George was in favour of pumping out the water from the top by powerful engines erected over each shaft, until the water was mastered. Robert concurred in that view, and although other engineers pronounced strongly against the practicability of the scheme and advised its abandonment, the directors authorised him to proceed; and powerful steam-engines were ordered to be constructed and delivered without loss of time. In the mean time, Robert suggested to his father the expediency of running a drift along the heading from the south end of the tunnel, with the view of draining off the water in that way. George said he thought it would scarcely answer, but that it was worth a trial, at all events until the pumping-engines were got ready. Robert accordingly gave orders for the drift to be proceeded with. The excavators were immediately set to work; and they were very soon close upon the sand bed. One day, when the engineer, his assistants, and the workmen were clustered about the open entrance of the drift-way, they heard a sudden roar as of distant thunder. It was hoped that the water had burst in--for all the workmen were out of the drift,--and that the sand bed would now drain itself off in a natural way. Instead of which, very little water made its appearance; and on examining the inner end of the drift, it was found that the loud noise had been caused by the sudden discharge into it of an immense mass of sand, which had completely choked up the passage, and prevented the water from flowing away. The engineer now found that there was nothing for it but to sink numerous additional shafts over the line of the tunnel at the points at which it crossed the quicksand, and endeavour to master the water by sheer force of engines and pumps. The engines erected, possessed an aggregate power of 160 horses; and they went on pumping for eight successive months, emptying out an almost incredible quantity of water. It was found that the water, with which the bed of sand extending over many miles was charged, was to a certain degree held back by the particles of the sand itself, and that it could only percolate through at a certain average rate. It appeared in its flow to take a slanting direction to the suction of the pumps, the angle of inclination depending upon the coarseness or fineness of the sand, and regulating the time of the flow. Hence the distribution of the pumping power at short intervals along
PREV.   NEXT  
|<   212   213   214   215   216   217   218   219   220   221   222   223   224   225   226   227   228   229   230   231   232   233   234   235   236  
237   238   239   240   241   242   243   244   245   246   247   248   249   250   251   252   253   254   255   256   257   258   259   260   261   >>   >|  



Top keywords:

engines

 

pumping

 

Robert

 

engineer

 

tunnel

 

sudden

 

workmen

 

George

 

erected

 

powerful


prevented

 

flowing

 

coarseness

 
inclination
 

shafts

 

additional

 
numerous
 
passage
 

depending

 

fineness


distribution

 

caused

 
intervals
 

discharge

 

completely

 

choked

 

immense

 

regulating

 

crossed

 

particles


examining

 

emptying

 

months

 

successive

 

percolate

 

charged

 

degree

 

extending

 

incredible

 

quantity


slanting

 

master

 

endeavour

 
suction
 

quicksand

 

direction

 

possessed

 

horses

 
average
 
aggregate