FREE BOOKS

Author's List




PREV.   NEXT  
|<   210   211   212   213   214   215   216   217   218   219   220   221   222   223   224   225   226   227   228   229   230   231   232   233   234  
235   236   237   238   239   240   241   242   243   244   245   246   247   248   249   250   251   252   253   254   255   256   257   258   259   >>   >|  
t pumping was necessary at many points to enable the works to proceed. For a year and a half the contractor went on fruitlessly contending with these difficulties, and at length he was compelled to abandon the adventure. The engineer then took the works in hand for the Company, and they were vigorously proceeded with. Steam-engines were set to work to pump out the water; two locomotives were put on, one at each end of the cutting, to drag away the excavated rock and clay; and 800 men and boys were employed along the work, in digging, wheeling, and blasting, besides a large number of horses. Some idea of the extent of the blasting operations may be formed from the fact that 25 barrels of gunpowder were used weekly; the total quantity exploded in forming this one cutting being about 3,000 barrels. Considerable difficulty was experienced in supporting the bed of rock cut through, which overlaid the clay and shale along each side of the cutting. It was found necessary to hold it up by strong retaining walls, to prevent the clay bed from bulging out, and these walls were further supported by a strong invert,--that is, an arch placed in an inverted position under the road,--thus binding together the walls on both sides. Behind the retaining walls, a drift or horizontal drain was provided to enable the water to run off, and occasional openings were left in the walls themselves for the same purpose. The work was at length brought to a successful completion, but the extraordinary difficulties encountered in forming the cutting had the effect of greatly increasing the cost of this portion of the railway. The Tunnels on the line are eight in number, their total length being 7336 yards. The first high ground encountered was Primrose Hill, where the stiff London clay was passed through for a distance of about 1164 yards. The clay was close, compact, and dry, more difficult to work than stone itself. It was entirely free from water; but the absorbing properties of the clay were such that when exposed to the air it swelled out rapidly. Hence an unusual thickness of brick lining was found necessary; and the engineer afterwards informed the author that for some time he entertained an apprehension lest the pressure should force in the brickwork altogether. It was so great that it made the face of the bricks to fly off in minute chips which covered his clothes whilst he was inspecting the work. The materials used in the buildin
PREV.   NEXT  
|<   210   211   212   213   214   215   216   217   218   219   220   221   222   223   224   225   226   227   228   229   230   231   232   233   234  
235   236   237   238   239   240   241   242   243   244   245   246   247   248   249   250   251   252   253   254   255   256   257   258   259   >>   >|  



Top keywords:

cutting

 

length

 

number

 

blasting

 

retaining

 

strong

 

encountered

 

forming

 

barrels

 

difficulties


enable

 

engineer

 

ground

 
Primrose
 

materials

 

compact

 
difficult
 
London
 

passed

 

distance


brought

 

successful

 
completion
 

purpose

 

openings

 

extraordinary

 

pumping

 

portion

 

railway

 

buildin


Tunnels

 

increasing

 

effect

 

greatly

 

pressure

 

apprehension

 

entertained

 

author

 

brickwork

 

altogether


minute

 

covered

 

bricks

 
informed
 

absorbing

 

properties

 

whilst

 

inspecting

 
occasional
 
exposed