FREE BOOKS

Author's List




PREV.   NEXT  
|<   411   412   413   414   415   416   417   418   419   420   421   422   423   424   425   426   427   428   429   430   431   432   433   434   435  
436   437   438   439   440   441   442   443   444   445   446   447   448   449   450   451   452   453   454   455   456   457   458   459   460   >>   >|  
With a rise of tide at springs of 18-3/4 ft., the average depth is thus approximately 66 ft. at high tide, necessitating a pressure of 29 lb. on the square inch, which is the limit at which men can work without inconvenience in the diving-bells. The breakwaters are raised about 11 ft. above high water of springs. The detached southern breakwater was finished off at this level; but the extended western breakwater, or Admiralty pier, is provided with a promenade parapet on its exposed side, rising 13 ft. above the quay; and the eastern breakwater also has a parapet on its exposed eastern side, raised, however, only 9 ft. above its quay. The breakwaters are protected from scour along their outer toe by an apron of concrete blocks, extending 25 ft. out from their sea face. [Illustration: Dover Breakwater. FIG. 13. South Breakwater. FIG. 14. Admiralty Pier Extension.] Concrete bag foundations. The levelling of the foundations for laying the courses of an upright-wall breakwater is costly and tedious, even in chalk; and the expense and delay are considerably enhanced where the bottom is hard rock. Accordingly, in constructing two breakwaters at the entrance to Aberdeen harbour on a bottom of granite in 1870-1877, concrete bags were laid on the sea-bed; and these bags, by adapting themselves to the rocky irregularities, obviated levelling the bottom. They formed the foundation for the concrete blocks in the south breakwater; and by the deposit of successive layers of 50-ton concrete bags till they rose above low water, they constituted the whole of the submerged portion of the north breakwater. The 50-ton bags were deposited from hopper barges towed out to the site; and the portions of both breakwaters above low water were carried up with mass concrete. Subsequently, the breakwater at Newhaven was constructed on a foundation of chalk, with lop-ton concrete bags up to low water, and mass concrete above. Still later, the two breakwaters sheltering the approach to the river Wear (see HARBOUR) and the Sunderland docks were built with a foundation mound of concrete in bags, 56 to 116 tons in weight, on the uneven sea-bottom, raised slightly above low water of spring tides, on which a solid upright wall was erected, formed of concrete blocks on each side faced with granite, filled in the centre and capped on the top with mass concrete. The mos
PREV.   NEXT  
|<   411   412   413   414   415   416   417   418   419   420   421   422   423   424   425   426   427   428   429   430   431   432   433   434   435  
436   437   438   439   440   441   442   443   444   445   446   447   448   449   450   451   452   453   454   455   456   457   458   459   460   >>   >|  



Top keywords:
concrete
 

breakwater

 

breakwaters

 

bottom

 

foundation

 

raised

 
blocks
 
Breakwater
 

exposed

 
Admiralty

eastern

 

parapet

 
foundations
 

levelling

 

granite

 

formed

 

upright

 

springs

 
Aberdeen
 
harbour

adapting

 

irregularities

 
deposit
 
successive
 

obviated

 

layers

 

weight

 
uneven
 

slightly

 

Sunderland


spring

 

centre

 

capped

 

filled

 
erected
 

HARBOUR

 
barges
 

portions

 
hopper
 

deposited


submerged

 

portion

 

carried

 
Subsequently
 

sheltering

 

approach

 

Newhaven

 

constructed

 

constituted

 
Extension