FREE BOOKS

Author's List




PREV.   NEXT  
|<   276   277   278   279   280   281   282   283   284   285   286   287   288   289   290   291   292   293   294   295   296   297   298   299   300  
301   302   303   304   305   306   307   308   309   310   311   >>  
foot pole was easily thrust down out of sight, perpendicularly, into it! Here was a dilemma! How could a heavy wall and building stand on that foundation? A skillful engineer was consulted, who had seen heavy brick blocks built in just such places, and who pronounced this a very simple case to manage. "If," said he, "the mud cannot get up, the wall resting on it cannot settle down." Upon this idea, by his advice, we laid our wall, on thick plank, on the clay, so as to get an even bearing, and drove down, against the face of the wall, edge to edge, two-inch plank to the depth of about three feet, leaving them a foot above the bottom of the wall. Against this, we rammed coarse gravel very hard, and left the bottom of the cellar one foot above the bottom of the wall, so that the weight might counterbalance the pressure of the wall and building. The building has been in constant use, and appears not to have settled a single inch. The cellar was first used only for manure, and for keeping swine. It was quite wet, and grew more and more so every year, as the water found passages into it, till it was found that its use must be abandoned, or an amphibious race of pigs procured. It was known, that the most of the water entered at the north corner of the building, borne up by the clay which comes to within three feet of the natural surface; and, as it would be ruinous to the manure to leach it, by drawing a large quantity of water through it into drains, in the usual mode of draining, it was concluded to cut off the water on the outside of the building, and before it reached the cellar. Accordingly, a drain was started at the river, some twenty rods below, and carried up to the barn, and then eight feet deep around two sides of it, by the north corner, where most water came in. We cut through the sand, and four or five feet into the clay, and laid one course only of two-inch pipe-tiles at the bottom. As this was designed for a catch-water, and not merely to take in water at the bottom, in the usual way, we filled the trench, after covering the tiles with tan, with coarse sand above the level of the clay, and put clay upon the top. We believe no water has ever crossed this drain, which operates as perfectly as an open ditch, to catch all that flows upon it. The manure cellar was then dry enough, but the other cellar was wanted for roots and implements, and the water was constantly working up through the soft clay bottom, keepin
PREV.   NEXT  
|<   276   277   278   279   280   281   282   283   284   285   286   287   288   289   290   291   292   293   294   295   296   297   298   299   300  
301   302   303   304   305   306   307   308   309   310   311   >>  



Top keywords:

bottom

 

cellar

 

building

 

manure

 

coarse

 

corner

 

consulted

 

twenty

 
engineer
 
started

carried

 

quantity

 
blocks
 

drains

 

drawing

 

ruinous

 

reached

 
Accordingly
 

draining

 
concluded

skillful

 
crossed
 

operates

 

perfectly

 

working

 

keepin

 

constantly

 

implements

 

wanted

 

designed


surface
 

filled

 
trench
 

covering

 

foundation

 

easily

 

gravel

 

Against

 

rammed

 

weight


constant

 

appears

 

counterbalance

 

pressure

 

thrust

 

perpendicularly

 
bearing
 

advice

 

resting

 

leaving