2-in. pipe per day. The average was much less,
owing to a variety of causes. At the end, the railway company added to
the contractor's force, and laid the last 10 miles of pipe in 7 days,
there being a half dozen separate gangs at work.
Along the railway, the day's record on wood pipe was 4,000 ft. of 11-in.,
6,200 ft. of 7-1/2-in. and 8345 ft. of 3-1/2-in, pipe laid by a gang of
eight men after the pipe was distributed along the trench. These eight
men, of whom five were Americans, laid 76 miles of pipe, and became
expert. Their operation was like the working of a clock.
On the 12-in. iron pipe, the regular day's work was 96 joints, or 1,152
ft. of pipe laid and caulked. The record was 1,644 ft. Two gangs laid
101,300 lin. ft. in 60 days. Such a gang consisted of 1 foreman, 1
inspector, 8 caulkers, 4 yarners, 1 melter, 1 pourer, 1 helper, and 10
men putting pipe into the trench.
_Cost Data_.--The pipe from Bonito to the railway was laid by contract.
The price was 18 cents per lin. ft. laid and back-filled from the
railway to the Nogal Reservoir, and 28 cents from Nogal to Bonito. In
addition, 50 cents per ton per mile was paid for hauling pipe, and extra
compensation for setting valves. From Coyote, east along the railway,
the work was done by the railway company under the writer's direction.
The total cost of laying 384,300 ft. of wood pipe, from 11 to 3-1/2 in.
in diameter, was $18,156.77, or 4.72 cents per ft., divided as follows:
Ditching $0.0249
Laying 0.0113
Back-filling 0.0110
-------
Total $0.0472
This includes unloading from the cars. Train service cost 1/3 cent per
ft. additional.
The pipe gang, including back-filling, consisted of 1 foreman, at $100
per month, one assistant foreman at $75, and about 30 Mexicans at $1 per
day. The rates were the same in the ditching gang. The plow team cost $6
per day.
Including all general expense, the cost does not exceed 6 cents per lin.
ft.
The cost of laying 101,300 ft. of 12-in. cast-iron pipe was $23826.67, or
23.5 cents per ft., divided as follows:
Ditching $0.0249
Laying 0.1180
Back-filling 0.0110
Lead 0.0790
Oakum 0.0014
-------
Total $0.2343
This includes train service and unloading pipe, but nothing for tools.
The foreman and inspector received $100 per month, the caulkers, $3;
pourer, $3; melter, $2.50; 2 pipe-men, $2, an
|