FREE BOOKS

Author's List




PREV.   NEXT  
|<   19   20   21   22   23   24   25   26   27   28   29   30   31   32   >>  
2-in. pipe per day. The average was much less, owing to a variety of causes. At the end, the railway company added to the contractor's force, and laid the last 10 miles of pipe in 7 days, there being a half dozen separate gangs at work. Along the railway, the day's record on wood pipe was 4,000 ft. of 11-in., 6,200 ft. of 7-1/2-in. and 8345 ft. of 3-1/2-in, pipe laid by a gang of eight men after the pipe was distributed along the trench. These eight men, of whom five were Americans, laid 76 miles of pipe, and became expert. Their operation was like the working of a clock. On the 12-in. iron pipe, the regular day's work was 96 joints, or 1,152 ft. of pipe laid and caulked. The record was 1,644 ft. Two gangs laid 101,300 lin. ft. in 60 days. Such a gang consisted of 1 foreman, 1 inspector, 8 caulkers, 4 yarners, 1 melter, 1 pourer, 1 helper, and 10 men putting pipe into the trench. _Cost Data_.--The pipe from Bonito to the railway was laid by contract. The price was 18 cents per lin. ft. laid and back-filled from the railway to the Nogal Reservoir, and 28 cents from Nogal to Bonito. In addition, 50 cents per ton per mile was paid for hauling pipe, and extra compensation for setting valves. From Coyote, east along the railway, the work was done by the railway company under the writer's direction. The total cost of laying 384,300 ft. of wood pipe, from 11 to 3-1/2 in. in diameter, was $18,156.77, or 4.72 cents per ft., divided as follows: Ditching $0.0249 Laying 0.0113 Back-filling 0.0110 ------- Total $0.0472 This includes unloading from the cars. Train service cost 1/3 cent per ft. additional. The pipe gang, including back-filling, consisted of 1 foreman, at $100 per month, one assistant foreman at $75, and about 30 Mexicans at $1 per day. The rates were the same in the ditching gang. The plow team cost $6 per day. Including all general expense, the cost does not exceed 6 cents per lin. ft. The cost of laying 101,300 ft. of 12-in. cast-iron pipe was $23826.67, or 23.5 cents per ft., divided as follows: Ditching $0.0249 Laying 0.1180 Back-filling 0.0110 Lead 0.0790 Oakum 0.0014 ------- Total $0.2343 This includes train service and unloading pipe, but nothing for tools. The foreman and inspector received $100 per month, the caulkers, $3; pourer, $3; melter, $2.50; 2 pipe-men, $2, an
PREV.   NEXT  
|<   19   20   21   22   23   24   25   26   27   28   29   30   31   32   >>  



Top keywords:
railway
 

foreman

 
filling
 

Bonito

 
Laying
 
trench
 
service
 

consisted

 

inspector

 

includes


unloading

 

melter

 

pourer

 

caulkers

 

company

 

laying

 

divided

 

record

 

Ditching

 

writer


direction

 

diameter

 

exceed

 

received

 
expense
 
assistant
 

including

 

additional

 

Mexicans

 

Including


general

 
ditching
 
helper
 

distributed

 

operation

 

expert

 

Americans

 

separate

 

variety

 
average

contractor
 
working
 

addition

 

Reservoir

 
filled
 

valves

 

Coyote

 

setting

 

compensation

 
hauling