FREE BOOKS

Author's List




PREV.   NEXT  
|<   192   193   194   195   196   197   198   199   200   201   202   203   204   205   206   207   208   209   210   211   212   213   214   215   216  
217   218   219   220   221   222   223   224   225   226   227   228   229   230   231   232   233   234   235   236   237   238   239   240   241   >>   >|  
greatest opportunity. Trench Construction.--The methods of building trenches are the same whether the work is carried on under fire or not. In an attack, upon reaching the limit of advance, the men immediately dig themselves in, and later connect these individual holes to make a continuous line of trench. Most of the digging must be done at night, and must be organized to obtain the most work with the least confusion. There are three ways of increasing the efficiency of the men. In the first of these, squad shifts, the squad leader divides his men into reliefs and gives each man a limited period of intensive work. Reliefs may be made by squads or by individuals. The second way of increasing efficiency is to induce competition among the man and squads, thus making the work a game in which each soldier's interest will be aroused in the effort to do better than the others. The third method is to assign a fixed amount of work to each man. An average task, which all ought to accomplish in a given time, is found by experience, and those who finish before their time is up are relieved from further work during that shift, and allowed to return to their shelters. Continual care must be used to check up the tools on hand, as the men are prone to leave them where they were working rather than carry them back and forth to work. Each unit must guard its property from appropriation by neighbors on its flanks. System of Laying Out Trenches.--The trace of the trench is first staked out, particularly at traverses and corners when the work is to be done at night. Measurements should be exact, and the men should be required to line the limits of each trench so as not to exceed them in digging. All sod should be taken up carefully and used on the parapet for concealment or on the berm to make a square back wall for the dirt of the parapet. If possible this should be done with the parados wall, so as to make it as inconspicuous as possible from the front. Men should begin to dig at the center of the trench and throw the dirt as far out on the sides as possible, so that as they go deeper the earth can be thrown just over the berm. The slope of the sides will be kept steep and the men prevented from widening the trench as they dig. In sandy soil the sides of the trench should be allowed to reach their angle of repose (which is wider at the top than required), then the trench walls supported with _revettments_ to the proper widt
PREV.   NEXT  
|<   192   193   194   195   196   197   198   199   200   201   202   203   204   205   206   207   208   209   210   211   212   213   214   215   216  
217   218   219   220   221   222   223   224   225   226   227   228   229   230   231   232   233   234   235   236   237   238   239   240   241   >>   >|  



Top keywords:

trench

 

efficiency

 
increasing
 

parapet

 

squads

 

required

 

allowed

 
digging
 

Measurements

 

traverses


working

 

corners

 

Laying

 
System
 
flanks
 

appropriation

 

neighbors

 
Trenches
 

property

 

staked


parados
 

prevented

 
widening
 

thrown

 

supported

 

revettments

 

proper

 

repose

 

carefully

 
concealment

square

 

limits

 

exceed

 
deeper
 

center

 
inconspicuous
 
confusion
 

obtain

 

continuous

 
organized

shifts

 
limited
 
period
 

intensive

 

reliefs

 

leader

 

divides

 
individual
 
connect
 

trenches