FREE BOOKS

Author's List




PREV.   NEXT  
|<   349   350   351   352   353   354   355   356   357   358   359   360   361   362   363   364   365   366   367   368   369   370   371   372   >>  
course, as may be found actually necessary, including possibly the change recommended by the Secretary of War as to the site of the dam on the Pacific side." On June 29, 1906, Congress provided that a lock type of canal be constructed across the Isthmus of Panama, of the general type proposed by the minority of the Board of Consulting Engineers, and work has continued along these lines. The Board of Consulting Engineers estimated the cost of the lock type of canal at $139,705,200 and of the sea-level canal at $247,021,000, excluding the cost of sanitation, civil government, the purchase price, and interest on the investment. These sums were for construction purposes only. I ventured a guess that the construction of the lock type of canal would approach $300,000,000, and without stopping to consider that the same causes which led to an increase in cost over the original estimates for the lock canal must affect equally the sea-level type, the advocates of the latter argued that the excess of the new estimates was an additional reason why the lock type should be abandoned in favor of the sea-level canal. The estimated cost by the present commission for completing the adopted project, excluding the items let out by the Board of Consulting Engineers, is placed at $297,766,000. If to this be added the estimated cost of sanitation and civil government until the completion of the work, and the $50,000,000 purchase price, the total cost to the United States of the lock type of canal will amount to $375,201,000. In the preparation of these estimates there are no unknown factors. The estimated cost of the sea-level canal for construction alone sums up to $477,601,000, and if to this be added the cost of sanitation and civil government up to the time of the completion of the canal, which will be at least six years later than the lock canal, and the purchase price, the total cost to the United States will aggregate $563,000,000. In this case, however, parts of the estimate are more or less conjectural--such as the cost of diverting the Chagres to permit the building of the Gamboa dam and the cost of constructing the dam itself. Much criticism has resulted because of the excess of the present estimates over those originally proposed, arising largely from a failure to analyze the two estimates or to appreciate fully the actual conditions. The estimates prepared and accompanying the report of the consulting engineers were
PREV.   NEXT  
|<   349   350   351   352   353   354   355   356   357   358   359   360   361   362   363   364   365   366   367   368   369   370   371   372   >>  



Top keywords:

estimates

 

estimated

 
Engineers
 

Consulting

 

construction

 

purchase

 

government

 

sanitation

 

excluding

 
excess

States
 

United

 

completion

 
present
 
proposed
 

engineers

 

amount

 
consulting
 

preparation

 
unknown

factors

 
accompanying
 
permit
 

building

 

Gamboa

 

Chagres

 
failure
 

analyze

 

largely

 
resulted

criticism
 

arising

 

constructing

 

diverting

 

originally

 

report

 

aggregate

 

estimate

 

prepared

 
conjectural

conditions
 
actual
 

continued

 

minority

 

Isthmus

 
Panama
 

general

 

interest

 

investment

 

constructed