FREE BOOKS

Author's List




PREV.   NEXT  
|<   56   57   58   59   60   61   62   63   64   65   66   67   68   69   70   71   72   73   74   75   76   77   78   79   80  
81   82   83   84   85   86   87   88   89   90   91   92   93   94   95   96   97   98   99   100   101   102   103   104   105   >>   >|  
platform was sunk to the head of the piles by the increasing weight of masonry. The center pier is octagonal, and is built in the same general manner as to foundations as the shore piers, but the piles are cut off 22 feet below water, and there are eighteen courses of timber in the grillage. The diameter of the platform between parallel sides is 53 feet, while that of the lower course of battered masonry is but 37 feet. The areas are as 2,332 to 1,147, or as 2 to 1 nearly. The pressure per square inch of timber on the heads of the piles is about the same as stated above for the shore piers. The number of piles under the center pier is 483. The risks and delays by this method of constructing the foundations were much less, and the cost also, than if an ordinary coffer dam had been used. Also the total weight of the piers is much less, as that portion below a point about two feet below the water adds nothing to their weight. The piles were driven with a Cram steam hammer weighing two tons, in a frame weighing also two tons. The iron frame rests directly upon the head of the pile and goes down with it. The fall of the hammer is about 40 inches before striking the pile. The total penetration of the piles into the clay averaged 27 feet. The settlement of the pile during the final strokes of the hammer varied from one quarter to three quarters of an inch per blow. There are 122 masonry pedestals, of which eight are large and heavy, carrying spans of considerable length. They will all be built upon concrete beds, except a few near the river on the north side, where piles are required. The four abutments with their retaining walls are of first-class rock-faced masonry. The footing courses are stepped out liberally, so as to present an unusually large bottom surface. They rest on beds of concrete 4 feet thick. The foundation pits are about 50 feet below the top of the bluffs, and are in a material common to the Cleveland plateau, a mixture of blue sand and clay, with some water. The estimated load of masonry on the earth at the bottom of the concrete is one and seven tenths tons to the square foot. Two of the large abutments were completed last season. They show an average settlement of three eighths of an inch since the lower footing courses were laid. The facts and figures here given regarding the viaduct were kindly furnished by the city civil engineer, C.G. Force, who has the work in charge.--_Jour. Asso. of E
PREV.   NEXT  
|<   56   57   58   59   60   61   62   63   64   65   66   67   68   69   70   71   72   73   74   75   76   77   78   79   80  
81   82   83   84   85   86   87   88   89   90   91   92   93   94   95   96   97   98   99   100   101   102   103   104   105   >>   >|  



Top keywords:

masonry

 

concrete

 
courses
 

hammer

 

weight

 

weighing

 

abutments

 

footing

 

platform

 
square

settlement

 
foundations
 
timber
 
center
 
bottom
 

present

 

liberally

 

unusually

 

surface

 

considerable


length

 

stepped

 

required

 

retaining

 

viaduct

 

kindly

 

furnished

 

figures

 
eighths
 

charge


engineer

 

average

 

plateau

 

Cleveland

 
mixture
 
common
 

material

 
bluffs
 
estimated
 

completed


season
 
tenths
 

foundation

 

stated

 

pressure

 

number

 

constructing

 

method

 

delays

 

manner