FREE BOOKS

Author's List




PREV.   NEXT  
|<   63   64   65   66   67   68   69   70   71   72   73   74   75   76   77   78   79   80   81   82   83   84   85   86   87  
88   89   90   91   92   93   94   95   96   97   98   99   100   101   102   103   104   105   106   107   108   109   110   111   112   >>   >|  
was something more important to bother about. Actions in Chancery had begun to distract the attention of worried directors, and these retarded progress with the construction of the line. So it was not until June 1869 that the Cambrian continued beyond Penmaenpool, and, even when Dolgelley was eventually approached, passengers had to alight at a platform some little distance from the town. Only when the Great Western Railway from Ruabon was completed did the trains from Barmouth Junction run into Dolgelley station proper. Many and difficult as were the engineering problems involved in the construction of the coast line none aroused greater interest or put scientific skill and courage to a severer test than that, to which we have already briefly alluded, of carrying the railway over the sand and river current into Barmouth. To the lay mind it appeared an almost insuperable task, and there were those who did not hesitate to whisper their doubts as to its practicability, one well-known local gentleman being reported to have gone as far as publicly to undertake to eat the first engine which ever crossed that formidable gulf. But engineers and craftsmen set to work with a will, and before long what had appeared an impossibility was rapidly taking shape as an actuality. Eight hundred yards in length, the greater portion was constructed on timber piles, over 500 in number, in 113 spans, driven into the sand. The navigable channel, at the Barmouth end, was crossed by an iron-work construction, of seven fixed and one opening span. The latter was of the drawbridge type, and when lifted at one end by means of large screws was carried on wheels and could be drawn back over the adjoining span. It was a lengthy as well as a cumbersome operation, and when, in 1899, the ironwork portion of the viaduct had become too weak for the constantly increasing loads of developing traffic, it was completely renewed with a modern steel structure of four spans, one of which was a spring span, revolving on the centre pier and giving two clear openings. The piers carrying the girders are formed of columns 8ft. in diameter sunk through the sand down to solid rock, which was reached at a depth of about 90 feet below high water mark. The columns are steel cylinders filled with concrete, and were sunk into position by means of compressed air on the diving bell principle, and owing to the depth below water at high tide, the men excavating insid
PREV.   NEXT  
|<   63   64   65   66   67   68   69   70   71   72   73   74   75   76   77   78   79   80   81   82   83   84   85   86   87  
88   89   90   91   92   93   94   95   96   97   98   99   100   101   102   103   104   105   106   107   108   109   110   111   112   >>   >|  



Top keywords:

construction

 

Barmouth

 

carrying

 

appeared

 

columns

 

greater

 

Dolgelley

 

portion

 

crossed

 

navigable


wheels

 

carried

 

hundred

 

channel

 

lengthy

 

taking

 

cumbersome

 

screws

 
actuality
 

adjoining


length

 
opening
 

number

 

timber

 

driven

 

constructed

 

lifted

 

drawbridge

 

modern

 
reached

cylinders
 

formed

 

diameter

 

filled

 
concrete
 
excavating
 
principle
 

position

 
compressed
 

diving


girders

 

increasing

 

constantly

 

developing

 

traffic

 

ironwork

 

viaduct

 

completely

 

renewed

 

giving