.
On July 1, 1890, Mr Mindeleff submitted a report. He described the ruins
of which Casa Grande is the type, and also Casa Grande itself. He also
made a statement of the condition of the ruin and suggested that the
main destruction "was due to the undermining of the walls, and stated
that much damage had been done by tourists. He recommended (1) that an
area about the ruin be fenced in; (2) that a man be located permanently
on the ground to watch the ruins; (3) that the ruins be cleaned out; (4)
that the walls be underpinned with brick instead of stone, as previously
suggested; (5) that the tops of the walls, after removing several inches
to afford a good bearing surface, be treated with a coping of cement. It
was regarded that this plan, if carried into effect, would afford
sufficient protection against the weather, but a plan for a roof was
submitted should such a structure be deemed desirable and practicable.
Mr Mindeleff also recommended a number of tie-rods and beams, the
replacement of the broken-out lintels, and the filling of the cavities
above.
This plan was approved in its general features, but the means provided
for its execution were found insufficient. A further complication arose
from the fact that a few months later Mr Mindeleff severed his
connection with the Bureau of Ethnology and his knowledge became no
longer available.
November 20, 1890, the writer was ordered to proceed to the ruin and
inaugurate the work of repair, following, so far as practicable, the
plans already approved. He left Washington soon afterward and reached
the ruin late in December. It was found necessary to make a detailed
survey of the ruin and of the group of which it forms a part, and to
make plans and sections showing the probable amount of excavation for
the use of those who were invited to bid on the work. Furthermore, the
amount appropriated was so well known to be inadequate that great
difficulty was experienced in obtaining bids, and it was only through
the efficient cooperation of the Reverend I. T. Whittemore at Florence
and of Mr C. A. Garlick at Phoenix that success was finally achieved.
Two bids were received from the former place and one from the latter;
but this was not accomplished until March 17, 1891, the date when the
last bid was received. In the meantime the writer, having completed his
work at Casa Grande, so far as he could, had entered, in January, on an
archeologic investigation of the valley of the
|